Status of Projects Undertaken by NHPC

PDF Print E-mail

Monday, 29 August 2011 22:24

Fourteen hydro-electric projects (HEPs) with an aggregate installed capacity of 5295 MW of NHPC are under operation. Another ten HEPs with total capacity of 4502 MW are under various stages of construction.

Out of these, Chamera-III (231 MW), Uri-II (240 MW) and Chutak (44 MW) HEPs are likely to be commissioned during the current year (Annex-I).

 

Giving this information in a written reply to a question in Rajya Sabha today the Minister of State for Power K.C.Venugopal said twelve more HEPs of NHPC, with an aggregate installed capacity of 9651 MW, are under various stages of development (Annex-II). He said in addition, seven projects with installed capacity of 2485 MW are under process of Survey & Investigation for preparation of Detailed Project Report (Annex-III). The Minister added that besides these, NHPC has also signed Memorandum of Understanding with Orissa Hydro Power Corporation Ltd. and Government of Orissa for formation of a Joint Venture Company to develop hydroelectric projects with an aggregate capacity of 320 MW in Orissa. He informed that the NHPC is also pursuing development of HEPs through Joint Venture in neighbouring countries like Bhutan, Myanmar, etc.

ANNEX-I

S No.

Project

State

Installed Capacity (MW)

Power Stations under Operation

1

Baira Siul

Himachal Pradesh

180

2

Loktak

Manipur

105

3

Salal

Jammu & Kashmir

690

4

Tanakpur

Uttarakhand

120

5

Chamera - I

Himachal Pradesh

540

6

Uri - I

Jammu & Kashmir

480

7

Rangit

Sikkim

60

8

Chamera - II

Himachal Pradesh

300

9

Dhauliganga-I

Uttarakhand

280

10

Dulhasti

Jammu & Kashmir

390

11

Teesta - V

Sikkim

510

12

Sewa-II

Jammu & Kashmir

120

13

Indira Sagar (NHDC-JV)

Madhya Pradesh

1000

14

Omkareshwar (NHDC-JV)

Madhya Pradesh

520

 

 

Total

5295

 

Projects under Construction

1

Teesta Low Dam - III

West Bengal

132

2

Chamera-III

Himachal Pradesh

231

3

Nimoo Bazgo

Jammu & Kashmir

45

4

Parbati - III

Himachal Pradesh

520

5

Teesta Low Dam - IV

West Bengal

160

6

Uri-II

Jammu & Kashmir

240

7

Chutak

Jammu & Kashmir

44

8

Subansiri (Lower)

Arunachal Pradesh/Assam

2000

9

Parbati - II

Himachal Pradesh

800

10

Kishanganga

Jammu & Kashmir

330

 

 

Total

4502

ANNEX-II

List of Projects awaiting statutory clearances/ Government approvals

S No.

Project

State

Installed Capacity (MW)

 

NHPC OWN’S PROJECTS

 

Kotli Bhel Stage - I A

Uttarakhand

195

Kotli Bhel Stage - I B

Uttarakhand

320

Kotli Bhel Stage - II

Uttarakhand

530

Teesta- IV

Sikkim

520

Dibang

Arunachal Pradesh

3000

Tawang-I

Arunachal Pradesh

600

Tawang-II

Arunachal Pradesh

800

 

 

Sub Total

5965

 

JV PROJECTS

 

 

 

JV between JKSPDC,NHPC & PTC Ltd.

 

Pakal Dul

Jammu & Kashmir

1000

Kiru

Jammu & Kashmir

600

Kwar

Jammu & Kashmir

520

 

JV between NHPC, Govt. of Manipur

 

Loktak Downstream

Manipur

66

 

JV between NHPC,SJVNL and Govt. of Manipur

 

12.

Tipaimukh

Manipur

1500

 

 

Sub Total

3686

 

 

Total

9651

ANNEX-III

List of Projects under DPR/FR stage

S No.

Project

State

Installed Capacity (MW)

1

Bursar

Jammu & Kashmir

1020

2

Lachen

Sikkim

210

3

Chhungar Chal

Uttarakhand

240

4

Garba Tawaghat

Uttarakhand

630

5

Khartoli Lumti Talli

Uttarakhand

55

6

Dhauliganga Intermediate*

Uttarakhand

210

7

Gori ganga IIIA*

Uttarakhand

120

Total

2485

 

* The Implementation agreement between NHPC and Govt. of Uttarakhand is yet to be signed. The same is under process.

Source : PIB

 



 